Haymarket is unusual, and it catches people by surprise. In 1994 the Town Council placed the entire town under a Historic District Zoning Ordinance, so there is no part of Haymarket where an exterior change is outside historic review. No building may be erected, reconstructed, altered or restored inside the town until the Architectural Review Board approves a Certificate of Appropriateness, and additions to existing buildings are named in the ordinance as covered work. After that you need zoning approval from the town, and only then does Prince William County issue the building permit. The county has handled building permits and inspections inside Haymarket since January 15, 2018. DLA Design and Build runs all three steps in order.
Three approvals, one sequence. Getting the order wrong is what costs the schedule.

Tell Us About Your Project

Fill out the form below and we will call you back to talk about your project.

Why Haymarket Homeowners Choose to Expand and Renovate

The town is 0.58 square miles and held 1,545 residents at the 2020 census. Almost every large community people mean when they say Haymarket, including Piedmont, Dominion Valley, Virginia Crossing and Woodborne Preserve, has a Haymarket mailing address and sits outside the town limits. So if you own a house on or near Washington Street and you want a comparable in-town house with a better floor plan, you are shopping a very small pool. Building onto what you own keeps the address, the walk to town and the lot.
Outside the town line the reasoning is different but lands in the same place. The larger-lot subdivisions outside the corporate limits have the land for a rear wing, a primary suite over the garage or a real screened porch, and the houses are new enough that the structure is rarely the problem. What stops people is their community's own HOA architectural committee and the Prince William County permit process, both of which are manageable if the drawings and the material list are prepared for them the first time.

Home Additions We Build in Haymarket, VA

DLA Design and Build works both sides of the town line in Haymarket, from a rear addition on a pre-1950 house on Washington Street to a primary suite wing in one of the larger-lot communities outside the corporate limits. Which approvals apply changes with the address, so that is the first thing we settle.

Room & Rear Additions Inside town limits we size room and rear additions to the R-1 rear yard of 25 feet, side yards of 10 feet each with 20 feet across both, and a 30 percent maximum lot coverage figure. Because the whole town is a historic overlay, the exterior of that addition also goes to the Architectural Review Board. Find Out More Second-Story Additions Haymarket's R-1 district allows 35 feet in height and up to three stories, and a second story adds nothing to the 30 percent lot coverage figure. On a pre-1950 house the ARB will look hard at massing and roof form, so we resolve the ridge line and the setback of the new mass at design stage, not at the hearing. Find Out More Primary Suite Additions We build primary suites with a full bath, walk-in closet and dedicated mechanical zoning. In the newer communities outside town this is the most common request we get, and the architectural review committee package is prepared in parallel with the county permit set rather than after it. Find Out More In-Law & Multigen Suites We design attached in-law and multigenerational suites with a private bedroom, bath and sitting area, plus step-free entry where the grade allows. Whether a proposed suite counts as an accessory living area or a separate dwelling unit is a zoning question we put to the town or the county before drawing it. Find Out More Sunrooms & Bump-Outs Sunrooms, screened porches and four to eight foot bump-outs add usable space without a full rear wing. Inside town limits they still need a Certificate of Appropriateness, because the ordinance covers any structure erected or altered within the Old and Historic Town of Haymarket. Find Out More Garage Additions Garages, driveways and parking areas all draw on Haymarket's 30 percent maximum lot coverage figure. In R-1 the setback line sits 35 feet from any street right-of-way 50 feet or wider, or 50 feet from the centerline where the right-of-way is narrower, which is a deep front setback and it shapes where a garage can go. Find Out More

Our Experience Working in Haymarket Neighborhoods

Inside the corporate limits the sequence is fixed. The Architectural Review Board comes first. The Town Council adopted the Historic District in 1994 and established the ARB at the same time, and no building, structure or sign may be erected, reconstructed, altered or restored within the Old and Historic Town of Haymarket until a Certificate of Appropriateness is approved by the Board or, on appeal, by Town Council. Review is limited to external architectural features subject to public view from a public street, way or place, and it explicitly covers rehabilitation of or additions to existing buildings. The Board meets the third Wednesday of each month at 7:00 PM at Town Hall on Washington Street, and it is required to meet within 45 days after the Town Clerk confirms an application is complete. A Certificate of Appropriateness expires one year after approval. Once the COA is in hand, town zoning approval follows, and only then does Prince William County Development Services issue the building permit and run the inspections, which it has done inside the town since January 15, 2018.
The 2021 zoning text amendment tightened the definitions, and one of them decides how hard your review will be: every building in the Old and Historic Town of Haymarket built before 1950 is a designated historic building. On a designated building, no architectural feature subject to public view may be altered without going to the ARB first. Interior remodeling is exempt, and so is routine maintenance, but the guidelines draw that line at ten percent, so replacing more than ten percent of a roof or a siding elevation is treated as material rather than routine. Outside the corporate limits none of this applies. Piedmont, Dominion Valley and the other large communities with Haymarket addresses sit in unincorporated Prince William County, where the county handles both zoning and building permits and the architectural review committee for your community is a private covenant matter rather than an ordinance. Those properties also sit in a Tidewater locality, so Prince William County's Chesapeake Bay ordinance applies, and any part of a lot within 100 feet of a perennial stream bank or adjacent wetland is a Resource Protection Area where development, land disturbance and vegetation removal are generally not allowed. We establish which of these tracks your parcel is on before design begins.

Frequently Asked Questions About Home Additions in Haymarket, VA

It depends on which side of the town line the parcel sits, and inside the line three approvals stack in a fixed order. Haymarket is an incorporated town in Prince William County. For an in-town property, the Architectural Review Board approves a Certificate of Appropriateness first, because the whole town is a historic overlay district. Then the Town of Haymarket issues zoning approval, which the town states is required before you submit a building permit application to the county. Then Prince William County Department of Development Services issues the building permit and every trade permit, including mechanical, electrical and plumbing, and performs the inspections. That county role has been in place since January 15, 2018, when the town transferred building permitting and inspections to the county. If your Haymarket address is in Piedmont, Dominion Valley, Virginia Crossing, Woodborne Preserve or any of the other communities outside the corporate limits, the town has no role at all and Prince William County handles zoning and building permits both. We confirm the parcel's jurisdiction before any drawing is started.

Inside the town limits, yes, and this is the part that surprises people. In 1994 the Town Council placed the entire town under a Historic District Zoning Ordinance, so there is no non-historic corner of Haymarket to build in. The ordinance provides that no building, structure or sign shall be erected, reconstructed, altered or restored within the Old and Historic Town of Haymarket unless and until an application for a Certificate of Appropriateness has been approved by the Architectural Review Board or, on appeal, by the Town Council. The town's own list of covered work names rehabilitation of or additions to existing buildings, new construction, and razing or demolition. Review is confined to external architectural features subject to public view from a public street, way or place, so the committee will not review your floor plan. Interior remodeling is exempt outright, and so is routine maintenance that does not significantly alter the appearance, though the design guidelines treat replacement of more than ten percent of a feature such as a roof or siding elevation as material rather than routine. We prepare the drawings, elevations and material specifications for that review as part of the design phase.

It changes how the Architectural Review Board treats the existing building. Under the 2021 zoning text amendment, all buildings within the Old and Historic Town of Haymarket that were built before 1950 are designated historic buildings. On a designated historic building, no architectural feature subject to public view from a public street may be altered, and no razing or demolition may proceed, without going to the ARB first. In practice that means the connection between the old house and the new work gets more attention than the new work does: where the addition meets the original wall, whether an original window or door opening is being lost, roof form and ridge height, and whether the addition reads as subordinate to the original from the street. The Board meets the third Wednesday of each month at 7:00 PM, is required to meet within 45 days of the Town Clerk confirming a complete application, and endeavors to announce a decision within 14 days of the final hearing. Aggrieved parties have 14 days to appeal to Town Council. An approved Certificate of Appropriateness is good for one year. We build that calendar into the schedule from the start.

Inside town limits the front setback usually makes the decision for you. In R-1 the setback line is 35 feet or more from any street right-of-way 50 feet or greater in width, or 50 feet from the centerline where the right-of-way is narrower, which pushes the buildable envelope well back on a 10,000 square foot lot. Add a 25 foot rear yard, 10 foot side yards totaling 20, and a 30 percent maximum lot coverage figure, and a rear addition can run out of room quickly. Going up avoids the coverage limit entirely, since a second story adds none, and the district allows up to 35 feet and three stories. The trade is the Architectural Review Board, which will look harder at a change in roof line and overall massing than at a single-story addition set behind the house. On a pre-1950 house we usually test a rear ell that continues the existing roof line first, because it satisfies both the setbacks and the review. Outside town limits, on the larger lots, the structure and the household usually decide rather than the ordinance. We model both on your parcel.

For an in-town Haymarket project, plan the approvals as three sequential steps rather than one. The Architectural Review Board meets monthly and must meet within 45 days of a complete application, so a Certificate of Appropriateness realistically accounts for one to two months on its own, longer if the Board asks for changes and the item returns to a later meeting. Town zoning approval follows, then Prince William County building permit review. Two to four months from design start to permit in hand is a fair planning range, and it moves with how complete the drawings arrive. Outside town limits, subtract the ARB and add your community's architectural review committee, which typically runs two to six weeks and can be filed alongside the county application rather than before it. Construction is separate: about three to five months for a single-story rear addition, sunroom or screened porch, and five to nine months for a second story, a primary suite wing or an in-law suite with a full bath and mechanical work. You get a dated schedule once the jurisdiction and the scope are confirmed.

On an in-town house, you design for the Architectural Review Board's actual test, which is whether the external architectural features subject to public view are architecturally compatible with the historic buildings in the district. The town's design guidelines are organized around Colonial, Federal and Folk Victorian forms with Greek Revival and Italianate detail, so the questions are roof pitch and ridge height, window proportion and muntin pattern, porch depth and column proportion, cornice and trim depth, and siding exposure. Where an original material cannot be matched in current production, we place the transition at an inside corner or a set-back plane rather than mid wall, and we set the addition back from the primary facade so the original reads first. In the newer communities outside town the questions are different and more mechanical: siding profile and exposure, shingle color that has weathered fifteen or twenty years, window brand and grille pattern, and carrying the roof pitch and overhang through cleanly. Either way we document existing conditions with photographs and measurements at the start and specify to match rather than approximate.

GOOGLE REVIEWS

What Our Clients Say

Real feedback from homeowners across Northern Virginia. We're proud of the relationships we build, project by project.

5.0 Average Rating
★★★★★
45+ Five-Star Reviews

How We Keep Haymarket Projects Efficient and Predictable

Addition projects are disruptive by nature, and the families we work with in Haymarket are living in the home during most of the build. We structure the work sequence to limit the period when major systems are open or exterior walls are exposed, communicate the schedule in plain terms before each phase, and keep the site clean and secured throughout. Minimizing disruption is part of how we plan the work.
A clear schedule and honest communication are the baseline we hold ourselves to.

The Result Haymarket Homeowners Are Looking For

When the addition is complete, it should be indistinguishable from the rest of the home in terms of finish quality, structural integrity, and how it reads from the street. Rooflines match, materials are consistent, and the new space connects to the existing floor plan in a way that feels considered rather than appended.

Contact DLA Design & Build in Haymarket

If you are planning a home addition in Haymarket, VA and want to know whether your parcel is inside the town's historic overlay or in unincorporated Prince William County, we are a straightforward conversation away.
Reach out and we will start with the specifics of your property.